KCSOS Development Dashboard

Sprint & Project Overview

Sprint performance, scope tracking, and project status — all in one place


Sprint Burnups

Avg Completion
70.1%
Target: 80%+
Avg Scope Creep
+15.2%
Effort added after sprint start
Best Sprint
S109
94% completed ✨
Worst Sprint
S103
44% completed
Total Delivered
2,303
of 3,747 pts committed

Completion Rate Trend

Percentage of total effort completed each sprint · Green ≥75% · Yellow ≥60% · Red <60%

Scope Creep by Sprint

% increase in total effort above guideline

Effort: Total vs Completed

Gap between committed effort and actual delivery

Sprint Detail

SprintScrum MasterDatesGuidelineTotal EffortScope CreepCompletedComp %Status

Key Insights

📉 Mid-Cycle Dip
Completion dropped from 78% (S96) to a low of 44% (S103) — a 34 percentage point decline over 7 sprints, coinciding with scope creep peaking at 22%.
🎉 New Record: 94%!
Sprint 109 hit 94% completion — smashing the previous best of 81% (S108)! Three consecutive strong sprints (79% → 81% → 94%) show the team is firing on all cylinders.
⚠️ Persistent Scope Creep
Average scope creep of 15.2% means teams consistently take on more work than planned. Sprints 98, 102, 103, 105, 108, 109, and 110 all exceeded 15%, with S109 hitting 28%.
🔍 Overcommitment Pattern
The team is delivering 2,303 of 3,747 total points (61% overall), suggesting capacity estimates need continued recalibration.

Project Tracker

Total Projects
33
Across all teams
Completed
18
55% of total
Project ↕ Due Date New Due Date Revised Due Date Original Done ↕